Resort re-design - new ocean-view deck, pool bar & grill, beach elevator and steps, hotel reception building.
BCM Construction Limited start on full conversion of Buildings D & G. New planning applications submitted for resort re-design.
While conversion of Buildings D & G continued apace, conversion of Buildings A & F started. Kate & Ambika joined the onsite sales team.
Conversion of Buildings B,E,H and J started. Planning approvals received for resort re-design and events lawn.
Construction starts on pool terrace, bar & grill, beach elevator & steps, restaurant, spa, and gym. A and F will complete. Model condos open to view.
Buildings B & E and the new reception & support buildings scheduled to complete.
All remaining amenities and condo buildings scheduled to complete. Hotel opens June 1, 2023.
Including:
Quarter 1 saw the start of conversion of Buildings D & G. Plus planning applications were submitted for the re-design improvements to the resort.
Conversion work on Buildings A & F started, while conversion of Buildings D and G continued apace.
In Quarter 2 of 2022 Bermudiana Beach Resort also welcomed Kate Martin and Ambika Scott to the onsite Sales Team!
Construction of pool area, pool bar & grill, beach elevator & steps, reception building, restaurant, spa, gym and hotel admin building started.
Conversion of Buildings B, E, H and J started.
Planning permission for resort design changes and the events lawn received.
Construction started on reception and support buildings.
Construction of pool area, pool bar & grill, beach elevator & steps, restaurant, spa, gym and hotel admin building starts.
Model condos in Buildings D & G scheduled to open to public viewing in the first week of October.
Work continues on Buildings H & J, the ocean-view deck, pool bar, grill, beach elevator and amenities building with its air-conditioned bar, lounge, restaurant, spa and gym.
New Reception and support building expected to be completed in March 2023.
Completing the reception building will allow the IT rooms to be set up, signifying the start of the launch countdown.
The fully air-conditioned amenity building with its bar, lounge, restaurant, indoor gym and spa is scheduled to complete by the end of May 2023.
The hotel scheduled to open on June 1, 2023.